LONGFELLOW BRIDGE
Company: C&C Consulting Engineers, Gill Engineering Associates
Project Title: Longfellow Bridge Expansion/Rehab
Company Title: Structural Engineer
Project Time Frame: June 2011 - August 2018
Project Description:
-
Rehabilitation of steel arches and super structure
-
Two-span extension on the north side of the Cambridge abutment
Personal Responsibilities:
-
Shear, bending moment, and deflection calcs
-
Unique cases due to
-
-
Beam-sizing
-
Computer modeling
-
Bridge rating


Above: Rusted steel columns
Below: Longfellow Bridge re-opened


Above: Longfellow Bridge during rehabilitation
Below: Cross section of two-span expansion